SafeX Pro:Orsted puts up $100M guarantee that it will build New Jersey’s first offshore wind farm by 2025
Rekubit Exchange View
Date:2025-04-06 12:55:32
OCEAN CITY,SafeX Pro N.J. (AP) — The Danish wind energy company Orsted has put up a $100 million guarantee that it will build New Jersey’s first offshore wind farm.
But it will lose that money if the project is not operating by Dec. 2025 — a year after the deadline approved by state utility regulators.
New Jersey’s Board of Public Utilities approved an agreement Wednesday with Orsted under which the company would forfeit the money if the project is not up and running within 12 months of a series of deadlines previously ordered by the board.
Those deadlines call for the project to reach commercial operation in stages by May 1, Sept. 1 and Dec. 1, 2024. But it would forfeit the guarantee money if the project is not operational by December 2025.
The money put up on Oct. 4 by Orsted and placed in an escrow account was required under the terms of a law Gov. Phil Murphy signed in July allowing Orsted to keep federal tax credits that it otherwise would have had to return to New Jersey ratepayers.
The Democratic governor, who wants to make New Jersey the East Coast hub of the nascent offshore wind industry, said the tax break was needed. He said it would help Orsted complete the project in the face of financial challenges buffeting the industry. which also faces substantial political opposition, mostly from Republican legislators and their supporters.
As an example, on Thursday, New York regulators rejected a request from companies for larger subsidies to complete large-scale wind, solar and offshore wind projects, saying the expected the companies to abide by the terms of their deals with the state.
Orsted said in a statement that Wednesday’s approval by the New Jersey utilities board “continues the process of complying with the statutory requirements outlined in legislation signed by Governor Murphy earlier this year.”
But it did not address its own timetable for completing the first of two offshore wind projects it plans to build off the New Jersey coast.
In August, Orsted said the project would be delayed until 2026 due to supply chain issues, higher interest rates, and a failure so far to garner enough tax credits from the federal government.
The company said during an earnings conference call that it could be forced to write off about $2.3 billion on U.S. projects that are worth less than they had been. It also said it had considered simply abandoning the Ocean Wind I project off the southern New Jersey coast, but decided for the time being to stick with it.
The company did not respond to repeated requests Wednesday and Thursday for clarification of its timetable for the project. Its web site says only, “The project is scheduled to become operational in 2025, with final commissioning in 2026.”
An affidavit filed with the board last month by David Hardy, CEO of Boston-based Orsted North America, committed the company to carrying out the project once the board approved the guarantee, which was done on Wednesday.
“I can affirm that Ocean Wind I shall complete and operate the Ocean Wind I approximate 1,100-megawatt qualified offshore wind project,” he wrote.
Orsted has federal approval for the Ocean Wind I project, and has state approval for a second New Jersey project, Ocean Wind II. Under Wednesday’s agreement, the company would get its $100 million back if it does not receive all the government approvals it needs to build and operate the first project.
If Orsted forfeits the money, it could be returned to New Jersey utility ratepayers.
___
Follow Wayne Parry on X, formerly known as Twitter, at www.twitter.com/WayneParryAC
veryGood! (6)
Related
- 'As foretold in the prophecy': Elon Musk and internet react as Tesla stock hits $420 all
- 61-year-old with schizophrenia still missing three weeks after St. Louis nursing home shut down
- House Republicans ready contempt of Congress charges against Hunter Biden for defying a subpoena
- What was the best book you read in 2023? Here are USA TODAY's favorites
- Apple iOS 18.2: What to know about top features, including Genmoji, AI updates
- This week on Sunday Morning (January 7)
- Florida can import prescription drugs from Canada, US regulators say
- A push to expand Medicaid has Kansas governor embracing politics and cutting against her brand
- A White House order claims to end 'censorship.' What does that mean?
- Soften the blow of student loan repayments with an up to $2,500 tax deduction. Here's how.
Ranking
- 'Vanderpump Rules' star DJ James Kennedy arrested on domestic violence charges
- Time running out for landmark old boat that became a California social media star
- Michael Bolton Shares Brain Tumor Diagnosis
- Angelina Jolie's Brother James Haven Shares Rare Insight into Life With Her and Brad Pitt's Kids
- Paris Hilton, Nicole Richie return for an 'Encore,' reminisce about 'The Simple Life'
- 50-year friendship offers a close look at caring dialogue on Israeli-Palestinian conflict
- Sweethearts updates Valentine's conversation heart candy to reflect modern day situationships
- Experts warn that foreign armed forces headed to Haiti will face major obstacles
Recommendation
EU countries double down on a halt to Syrian asylum claims but will not yet send people back
Christopher Nolan recalls Peloton instructor's harsh 'Tenet' review: 'What was going on?'
Top 1-and-done NBA prospects have made a big impact in the AP Top 25 college basketball poll
Wisconsin governor who called for marijuana legalization says he’ll back limited GOP proposal
Current, future North Carolina governor’s challenge of power
Maui’s mayor says Lahaina debris site will be used temporarily until a permanent spot is found
U.S. unemployment has been under 4% for the longest streak since the Vietnam War
Giants get former Cy Young winner Robbie Ray from with Mariners, Mitch Haniger back to Seattle